Do poly sheeting walls and floors need to be hung independently from one another under regulation 8?

Yes

Under Regulation 8, when constructing a containment area for asbestos abatement, poly sheeting walls and floors must indeed be hung independently from one another. This requirement is in place to ensure that the containment system is fully sealed and effective in preventing the release of asbestos fibers into the surrounding environment. By having separate installations for wall and floor sheeting, you minimize the possibility of compromising the integrity of the containment area, which is essential for worker safety and public health.

This independent installation allows for better management of potential leaks or breaches, as any issues can be addressed without affecting both barriers simultaneously. Moreover, it facilitates easier maintenance and adjustments during the abatement process, ensuring ongoing compliance with safety regulations. Having poly sheeting wall and floor systems that are independently hung creates a more reliable and safe containment environment during asbestos removal and remediation work.

Get further explanation with Examzify DeepDiveBeta

No

Only for larger projects

It depends on the materials used

Next Question

Report this question

Subscribe

Get the latest from Examzify

You can unsubscribe at any time. Read our privacy policy